fnPrime




« Back to Facilities Management News Home

« Elevators

Western Specialty Contractors: Crew Cuts Elevator Opening Through 5 Floors at Minnesota Senior Community


 

St. Louis, Mo. — June 21, 2016 — Elevators are a welcome convenience for buildings with multiple floors, but when a new elevator is planned for an existing, occupied structure, the construction process can be challenging.

Western Specialty Contractors - Minneapolis Branch overcame a variety of challenges including unforeseen utilities, heavy tenant traffic, and a tight schedule when it was recently tasked with cutting an elevator opening through five, post-tension cable decks at the Village Shores Senior Community in Richfield, Minn. (See photo.)

The scope of work included removal of 540 square feet of 7.5-inch-thick concrete from the ground-floor parking garage upward through to the building's fifth floor, detension of 58 PT tendons, installation of new anchors and cages outside the elevator opening, and retension of 116 tendons. 

The Village Shores Senior Community is a 10-story building which sits atop a ground-level parking garage. Commercial tenants occupy the first floor and senior community tenants occupy floors 2 through 10. The building was 99 percent occupied at the time of the project.

The first challenge Western crews faced on the project was maintaining the owner's tight schedule of completing one floor per week. Western was able to accommodate the owner's goal by maintaining a strict schedule that called for completing a particular task on the day that it was assigned.

The owner also gave Western crews just two days a week, Monday and Tuesday, to make noise on the project for removing concrete and installing rebar and new anchors. Noise was not permitted during the rest of the week.

The first opening Western cut in the parking garage ceiling posed an unforeseen challenge of its own. The deck had a construction joint and four perpendicular PT tendons running right through it that required Western to detension four additional tendons and move them out of the work area.

Unforeseen electrical mains were discovered at the openings of floors four and five, which were not on the plans. To resolve the obstacle, Western worked with the owner and the project electrician to have the mains re-routed so Western's work could continue.

As Western crews ascended the floors of the structure, they faced additional challenges. They were not allowed to use the only functioning elevator on the site, which was reserved for tenant use, to stage materials or remove concrete rubble. Western overcame this challenge by lowering rubble down the outside of the structure onto the second floor where it could be dropped through a trash chute to a dumpster.

Western crews were able to complete the two-month project in June 2016, on time and within budget. The architect on the project was Built Form, LLC; Stevens Construction Corp. was the project consultant; and Fink Horesch, LLC was the engineer.

Family-owned and operated for 100 years, Western Specialty Contractors is  a specialty contractor in masonry and concrete restoration, waterproofing, and specialty roofing. For more information, visit www.westernspecialtycontractors.com.                     

 





Contact FacilitiesNet Editorial Staff »   posted on: 6/27/2016


More From 6/27/2016 on FacilitiesNet