Aquatherm Piping Used in Novva's New Data Center Outside of Salt Lake City

The use of Aquatherm’s piping was driven by the need for adequate cooling.   April 14, 2023


By FacilitiesNet Staff


Businesses that entrust their data storage to the state-of-the art Novva data center outside of Salt Lake City, Utah, will benefit from a location chosen for its many data center-friendly attributes. The area offers outstanding connectivity, low power costs and a central-western site with easy access to a major international airport. In addition, the site’s climate and 5,000-foot altitude allow for many hours of free cooling annually. 

Just as important to Novva’s clients, the new data center has a low disaster risk. The area is not prone to earthquakes, floods or adverse weather events such as hurricanes. 

Finally, the cooling system for the computer servers boasts Aquatherm PP-RCT piping that will provide virtually leak-free service for decades to come. The Aquatherm piping will never scale or corrode, and the cooling water flow will remain unchanged throughout the anticipated 50-year lifespan of the pipe. 

The “hyperscale” data center in Salt Lake City will be Novva’s flagship data center. The 100-acre Utah campus is planned to ultimately include more than 1.5 million square feet of data center space and will accommodate 250-kilowatt to 30-megawatt clients. The construction is taking place in four phases. The first phase, which includes a 300,000 square foot data center, a 120-megawatt substation and an 80,000 square foot headquarters office building for Novva, was completed in December 2021. 

Reliable cooling systems are an essential component of modern data centers. Computer servers are notorious for generating heat—and heat is notorious for being an enemy of computer servers. 

The decision to install Aquatherm pipe as part of the new data center’s cooling system was driven by Steven Boyce, vice-president of infrastructure and design at Novva Data Centers. Boyce has been involved in the IT and data center space for more than 20 years and has worked on multiple successful startups during that time. 

Once the decision was made to trust the cooling system’s performance to Aquatherm pipe, Novva turned to the Salt Lake City branch of Harris Mechanical for the installation. 

Harris had experience installing Aquatherm pipe, although the Novva data center represented the company’s largest data center Aquatherm installation to date. To handle the first phase of the Novva system, Harris installed a BASX custom chiller package (which included the pumps and controls), the Aquatherm pipe for computer system cooling and the comfort system piping and plumbing. The piping work for phase 1 began in mid-May 2021 and was completed in October 2021. The system was commissioned and turned over to the owner in December 2021. 

Jeff Reading, operations manager, construction, Harris Mechanical, explained that the Novva data center started out as a core and shell project, with the office built first and the data hall scheduled to be built out later. 

“We finished the core and shell construction in May 2021, and the data hall was right on its heels as a change order to the original project. So, it came at us fast and furious,” Reading says. “The original plan was to complete the entire chilled water loop, which runs underneath the floor on both sides of the building. However, it was decided to install the piping in stages as the facility is built out. So far, we have installed about half of the piping that will ultimately go in there.” 

The installation to date has included 4,418 feet of Aquatherm Blue Pipe SDR 17.6. The main system piping is 10 inches, and the takeoffs are four inches. 

To handle such a large project. Harris Mechanical sent several installers to Aquatherm’s U.S. headquarters in nearby Lindon, UT, for training. 

Aquatherm training is the most intensive, comprehensive training in the polypropylene piping industry. Attendees receive both classroom training and hands-on training with multiple fusion machines and must pass a rigorous test using all the fusion tools correctly. 

After the training, Harris completed the installation using McElroy fusion tools and a combination of socket fusion for the four-inch pipe and butt fusion for the 10-inch pipe. The system runs at a low pressure (35 to 45 pounds per square inch); the cooling system supply water runs at 55 degrees Fahrenheit and returns to the chiller at about 60 degrees Fahrenheit. 

According to Reading, Harris Mechanical had a good experience with Aquatherm piping at the Novva data center, and the ease of installation compared to steel pipe helped Harris stay ahead of the project’s tight schedule. 

The underfloor piping system presented one of the major installation challenges at this project. The floor is raised 5 feet, and all of the facility’s piping, wiring, HVAC ducting and utilities run through the raised space. 

Aquatherm’s building information modeling (BIM) capabilities and Scan-to-Fab service helped ensure that the installation went smoothly by preventing underfloor conflicts and collisions. 

“Using 3D BIM and Revit really helped with coordinating this installation,” says Autumn Turner, a fabrication drafter at Aquatherm. “Not only was all the HVAC and plumbing under the floor, there were floor stands every square foot. It took a lot of coordination to avoid all those potential obstacles.” 

“Aquatherm is just easier to work with than steel pipe,” Turner says. “It takes a lot less time to weld, and when you add in the BIM support and drafting it was easier for the installers to get situated into the floor and navigate the space.” 

Turner added that Aquatherm’s BIM and Revit capabilities will ensure the future installation phases of the massive project also go smoothly. 

Next


Read next on FacilitiesNet