fnPrime



Summer Work Common to Complete Upgrade Projects in K-12 Facilities

Summer Work Common to Complete Upgrade Projects in K-12 Facilities



Part five of a six-part article on funding K-12 retrofit projects


By Dave Lubach, Associate Editor  
OTHER PARTS OF THIS ARTICLEPt. 1: Money Matters: K-12 Education Facilities Tackle Retrofit FundingPt. 2: Financing Hurdles Tough to Overcome in K-12 DistrictsPt. 3: Managers' Roles Vary in Trying to Secure Funding for K-12 RetrofitsPt. 4: Return on Investment Factors into K-12 Retrofit DecisionsPt. 5: This PagePt. 6: Future Focus: What's Your Next Retrofit Project?


Managers who successfully secure funding for upgrades to facilities and systems know they have to deliver on the promises made along the way. In many districts, the time for action is summer, the three-month window when students are away and staffs have full access to schools.

“Our biggest challenge isn’t necessarily getting the work done but dealing with the time constraints we have in the public school sector,” says Roger Fritz, the manager of construction management with Frederick County Public Schools. “We have to have these kinds of projects completed over the summer.”

Earlier starting times for school districts also cut into the time staffs have to finish projects, so while students are in class, managers are often planning summer work schedules for employees and lining up contractors for projects.

“We take a lot of our school year designing and planning projects, but there is a great deal of urgency for getting projects done in the summer,” Fritz says. “Many of my project managers wind up working long hours, sometimes even weekends. It’s just part of what we have to do to have the schools ready.”




Contact FacilitiesNet Editorial Staff »

  posted on 2/12/2016   Article Use Policy




Related Topics: